Building update from Captain Richard
06/20/08
The construction of the new UU Center has been proceeding very strongly. As of June 18, the entire shell of the building has been constructed, framing of the rooms at the sanctuary level is complete, and framing of the classroom level rooms is underway. Under-floor plumbin -
The sad saga of the sod
06/03/08
Our Watering Wizards are a team of dedicated volunteers that spend 90 to 120 minutes each day watering the areas where we are required to grow grass, in order to stabilize the soil around the retention basin, so as to prevent erosion.
There was some erosion occurring due to recent h
-