Septic done and steel started
03/20/08
The backfilling is now done and you can walk up to the classroom level concrete walls and peer in. Below you can see the piers for the back deck (east side of the building).
The steel (by New Jersey Iron Co.) is starting to be erected and you can see now how tall the building -
Classroom level walls are up
03/13/08
During the last week of February, the concrete was poured that will form the walls of the classroom (lower) level. Here you see Richard and Chris reviewing plans for the walls on the south side, where the stairwell will be.
I'm guessing Chris has little fear of heights, a
-
Septic done and steel started