Excavation and site work
01/20/08
The earthmovers are here!
The top soil has been moved into large piles:
They're digging out the retention basin (it's huge!):
And are grading the area (below, to the left is where the actual building will be). The crushed stone drive -
Status of work and timeline
01/18/08
Tree Removal -- Complete
Charles Auchter completed his work in record time and did an excellent job. We actually adjusted our clearing line wherever we could save an extra tree.
Earth Work -- 20% complete
The top soil has been removed and placed in two piles for fut -
Goodbye trees
01/17/08
We're very sorry to see the trees go....
but construction is really, truly, finally under way!
The area was cleared during the week of January 7 thru 11.
The top picture was taken at our Groundbreaking, November 18, 2007.
The remainder were taken January 8,9, a
-
Excavation and site work